The East Harbor is the Marina's other boat basin, tucked between the West Harbor and Pier 1 at Fort Mason. On land it has sidewalks, green space and public parking, and on the water it has docks. It also has the Gashouse Cove fuel dock, and that name points to the harbor's history. In the late 1800s and early 1900s, PG&E and the companies before it ran the North Beach Manufactured Gas Plant on part of what is now the East Harbor. A second plant, the Fillmore Manufactured Gas Plant, stood just southwest of it.
The sediment those plants left behind decides where the planned waterfront park's water-access features go and when they arrive.
What Two Gas Plants Left in the Mud
Manufactured gas plants made fuel gas by heating coal and oil. PG&E's own explainer says the process produced coal-tar and lampblack byproducts, which were often left buried at the old plant sites.
Later testing found polycyclic aromatic hydrocarbons, a group of compounds called PAHs, in the sediment of the East Harbor and of the water just north of it, which regulators call the Outside East Harbor. The San Francisco Bay Regional Water Quality Control Board links those compounds to the operations of both former plants.
The paperwork has taken years. PG&E and San Francisco Recreation and Parks sent draft feasibility studies to the Water Board in March 2023, and the studies were finalized in June 2025. PG&E submitted its Remedial Action Plan on December 12, 2025, and revised it on April 29, 2026. The plan calls for:
- dredging the affected sediment
- capping deeper contamination in place
- installing reactive barriers along the shoreline
- monitoring after the work is done
Why the Old Mud Turns Boat Slips Into a Basin
Over more than a century, clean sediment has settled on top of the contaminated layer. Rec and Park's April 16, 2026 staff report says a risk assessment found that this natural cover is effectively isolating the sediment with higher PAH levels. It also found that dredging the harbor deep enough for full marina use would strip that clean cover and require an engineered cap.
That finding splits the East Harbor in two. The upper portion will be dredged to navigation depth, and engineered cap material will go over much of it. The lower basin will not be dredged at all, so its natural cover stays in place over the deeper contamination. Left undredged, that water is too shallow for boats. The plan moves the southern East Harbor berths elsewhere and keeps the northern East Harbor as a marina.
The southeast corner, where boats will no longer fit, becomes a shallow-water basin of about five acres with an upland area next to it. The staff report describes it as "a place for all to have access to the water, even if they do not own a boat." The department says the features for this area came from comments it collected during community outreach. The list includes:
- an accessible dock with a built-in kayak launch
- direct water access
- a softened shoreline and a reconfigured Bay Trail along the East Harbor
- a nature exploration area
- a lawn and viewpoints
- one or more volleyball courts
- improved public restrooms, plus a separate restroom for boaters
The breakwaters change too. The plan adds a new breakwater running from the Jetty past the Wave Organ and a second one extending from the existing East Harbor breakwater. It also upgrades the current East Harbor breakwater so the public can walk out on it. The staff report says that walkway was added because of community feedback and describes it as offering "amazing views to the Bay and Alcatraz."
The Bay Trail section along the East Harbor is part of a 356-mile route around San Francisco Bay, according to the San Francisco Examiner's coverage of the approval.
The cleanup and the most public part of the park are in the same corner of the harbor. The cleanup has to happen first, so this corner is scheduled to change last.
The Order the Work Is Planned In
The Recreation and Park Commission unanimously approved the concept design for the Marina Improvement and Remediation Project on April 16, 2026. The staff report says plainly that the marina improvements "will be undertaken after PG&E completes a remediation project," which the Water Board oversees. Because of that, the work is split into phases by harbor.
| Milestone | Date in the most recent public documents | Source |
|---|---|---|
| Concept design approved | April 16, 2026 | Rec and Park |
| Public comment on the cleanup plan | May 15 to June 15, 2026 | Water Board |
| Cleanup plan finalized | Expected late 2026 | Water Board |
| Construction contract advertised | Expected fall 2026 | Rec and Park |
| Contract bid and award | Late 2026 in the staff report schedule | Rec and Park |
| West Harbor park and breakwater work begins | Mid-2027 | Rec and Park, Examiner |
| East Harbor sediment cleanup | Planned for 2027 to 2028 | Water Board |
| East Harbor marina work begins | Mid-2028, after the cleanup | Examiner |
Rec and Park's April update said the team was finishing construction documents and that construction would start in mid-2027. The staff report estimates about three years of construction from that start. The Examiner reported that the first phase covers park improvements and breakwater work in the West Harbor. The East Harbor marina work is expected to follow the cleanup in mid-2028.
All of these dates are targets from spring 2026 documents. Together they set the order: work starts on the Wave Organ side and moves east toward Fort Mason.
What Happens to Gashouse Cove's Fuel Dock
As part of the plan, the Gashouse Cove fuel dock in the East Harbor will be closed and moved to a West Harbor location that has not been chosen yet. The Examiner reported that project manager Monica Scott said Rec and Park is working with the Port of San Francisco and other stakeholders to find a new site that can sell gasoline and diesel.
Tamara Sokolov, a program leader for the San Francisco Sea Scouts, told the Examiner that once the current station closes, the nearest fuel dock is at Richardson Bay in Sausalito:
"You have to burn a lot of fuel to get fuel. If you're a boater in San Francisco, that's really problematic to us."
The Sea Scouts teach young people to sail, row and kayak. They run a motorboat that serves as an emergency towing vessel and a diesel training boat that teaches engine maintenance. Sokolov said that fueling in Sausalito could reduce the number of training sessions and how often safety boats can go out with sailboats and kayaks.
More Slips Than Today, Fewer Than the 2023 Plan
The slip count makes more sense next to two baselines. According to the Examiner, the East Harbor has 128 slips and the West Harbor has 347, for a combined 475. The approved plan would raise that to 536.
That is 61 more slips than today, but 170 fewer than the version presented to the commission in October 2023. The staff report says the reduction follows a February 2024 Board of Supervisors ordinance that limits how far the West Harbor marina can expand. Some berths are also getting larger, from 20 to 25 feet up to 30 to 35 feet, because the department found those sizes are in higher demand at marinas around the Bay Area. For shorter boats, the department is planning side-tie spaces.
Sokolov told the Examiner she wished the plan added more mooring space. She said the shortage has pushed boats to places like South Beach Harbor near Oracle Park.
Dredging, the Other Reason the Harbor Is Being Redesigned
The plan also targets a cost the harbor already carries. The staff report lists shoaling and sediment buildup among the problems it addresses, which "today results in frequent dredging" and higher operating and maintenance costs. The new breakwaters are meant to help with that.
Dredging is already a regular part of how the harbor runs. The Marina Harbor Association reported that spring dredging at the West Harbor entrance finished June 28, 2026, and that another round was expected in October. Rec and Park has also posted a West Harbor pre-dredge hydrographic survey dated September 25, 2026. That survey is part of routine West Harbor maintenance. It is separate from the PG&E cleanup in the East Harbor, which the Water Board has scheduled for 2027 to 2028.
The next two milestones on the published schedule are the Water Board's final approval of the cleanup plan, expected in late 2026, and Rec and Park's advertisement of the construction contract, expected this fall. Both are scheduled to come before construction on the park or the East Harbor cleanup begins.
If you are weighing a move near Marina Green, or you own nearby and want to know how a multiyear construction schedule might affect your plans, The Weisinger Group can walk you through the timeline and what it means for your situation. Schedule a consultation.